City

Mouchak-Moghbazar flyover opens to traffic

Prime Minister Sheikh Hasina today formally opened the 8.7km Mouchak-Moghbazar flyover to public with the 4km Malibagh-Razarbagh-Shantinagar section ready for traffic.

She inaugurated the flyover through video conferencing from her official Gono Bhaban residence at 12:35 pm.

Earlier, the flyover construction had drawn constant public wrath for tattered roads and traffic mismanagement underneath and was marred with accidents and onsite causalities time and again.

The premier in March last year inaugurated the first phase of two-kilometre four-lane carriageway section of the flyover stretching from Shaheed Captain Mansur Ali Sarani near Holy Family Hospital to Saat Rasta intersection (Shaheed Tajuddin Ahmad Sarani).

The project was originally scheduled to start in 2011 and completed by December 2015, but it started in 2013.

In January 2015, the Executive Committee of the National Economic Council approved a revision of the project with an extension of 18 months till June 2017 and an increase in the cost by Tk 446.2 crore.

The scheme is financed jointly by the Saudi Development Fund, OPEC Fund for International Development and the Government of Bangladesh.

 

 

Comments

Mouchak-Moghbazar flyover opens to traffic

Prime Minister Sheikh Hasina today formally opened the 8.7km Mouchak-Moghbazar flyover to public with the 4km Malibagh-Razarbagh-Shantinagar section ready for traffic.

She inaugurated the flyover through video conferencing from her official Gono Bhaban residence at 12:35 pm.

Earlier, the flyover construction had drawn constant public wrath for tattered roads and traffic mismanagement underneath and was marred with accidents and onsite causalities time and again.

The premier in March last year inaugurated the first phase of two-kilometre four-lane carriageway section of the flyover stretching from Shaheed Captain Mansur Ali Sarani near Holy Family Hospital to Saat Rasta intersection (Shaheed Tajuddin Ahmad Sarani).

The project was originally scheduled to start in 2011 and completed by December 2015, but it started in 2013.

In January 2015, the Executive Committee of the National Economic Council approved a revision of the project with an extension of 18 months till June 2017 and an increase in the cost by Tk 446.2 crore.

The scheme is financed jointly by the Saudi Development Fund, OPEC Fund for International Development and the Government of Bangladesh.

 

 

Comments

ঘন কুয়াশায় ঢাকা-মাওয়া এক্সপ্রেসওয়েতে একাধিক গাড়ির সংঘর্ষ, নিহত ১

মাওয়ামুখী লেনে প্রথমে একটি প্রাইভেট গাড়িকে পেছন থেকে ধাক্কা দেয় একটি কাভার্ডভ্যান। তারপরে একটি বাস প্রাইভেট গাড়িকে পেছন থেকে ধাক্কা দেয়। কাভার্ডভ্যানের পেছনে এসে ধাক্কা দেয় আরেকটি মাইক্রোবাস।...

৫১ মিনিট আগে